Develop a pipeline management plan

You must have an approved pipeline management plan in place prior to:

  • applying for a consent to construct or operate a pipeline
  • modifying a pipeline
  • decommissioning a pipeline.

A pipeline management plan may provide for one or more pipelines.

Stages covered by pipeline management plans

A pipeline management plan may be submitted for one or more of the following stages for the pipeline:

  • design and construction
  • operation
  • modification
  • decommissioning.

 A pipeline management plan may cover one or more of these stages.

Contact the Energy Division on (08) 8999 5460 (operations) for more detailed information on this process.

Content of a pipeline management plan

Before developing your pipeline management plan you must reach agreement with the Minister on the content of the plan. 

You must also agree the scope of validation.

Your plan must include all of the following information for the stage of your pipeline:

  • description of your strategic health and safety objectives
  • description of the pipeline including:
    • design
    • route corridor
    • composition of materials to be conveyed
  • description of your pipeline management system
  • description of the standards applying to the pipeline
  • arrangements for recording, storage and access to pipeline related documents
  • arrangements for reporting on pipeline activities 
  • arrangements for managing the integrity of assets
  • an environmental management plan.

Read the Energy Pipelines Regulations sections 26-32 for detailed information about developing your plan.

Acceptance of the pipeline management plan

You must submit your plans for construction or operation to the Minister for acceptance once validated by an independent pipeline expert as being fit for purpose and meeting required standards. The validator's report must also be submitted with your plans.

Other plans still in development (eg for commissioning activities) may be submitted to the Minister for acceptance upon completion of development.

Contact the Energy Division on (08) 8999 5460 (operations) for more detailed information on this process.

How to submit the pipeline management plan

You can submit your pipeline management plan by post, fax, email or by hand:

Department of Primary Industry and Resources
Attn: Executive Director, Energy
Energy Division
GPO Box 4550
Darwin NT 0801
Fax: (08) 8999 5191
petroleum.operations@nt.gov.au

Department of Primary Industry and Resources
Attn: Executive Director, Energy
Energy Division
4th Floor Centrepoint Building
The Mall
Darwin NT 0800

Last updated: 13 October 2017